Generators
Dr Peadar Grant
Data Centre Infrastructure
1 Load types
-
Critical
- loads cannot lose power, even momentarily.
-
Essential
- loads can tolerate a brief power interruption, but will need to be operational for continued running of the
data centre.
-
Non-essential
- loads are discretionary and can be done without.
The classification of any particular load will depend on the business needs. The same load might be classed as critical, essential
or non-essential in different contexts.
2 Standby generators
A UPS normally protects critical loads for a short period of time. For longer power outages, a separate generator is
required.
Standby generators are usually supplied as a package unit, containing:
-
Prime-mover
- normally a reciprocating diesel engine.
-
Alternator
- to convert mechanical energy into electrical energy.
-
Controls
- including a governor to control engine speed, determining frequency, and an automatic voltage regulator to
control the excitation in the generator’s windings, determining output voltage.
Figure 1: Diesel generator schematic
3 Power system including Generator
The generator normally powers the essential and (via the UPS) the critical loads, section 2.
4 Transfer sequence
The transfer is usually managed by an automatic transfer switch. This is a “break-before-make” switch that disconnects the
power from the mains and transfers it to the generator. The transfer switch is normally interlocked with the generator’s control
system so that the generator starts on a loss of power.
4.1 On loss of mains power
- Power is lost in the mains (i.e. voltage goes out of range). This causes the automatic transfer switch (ATS) to
start a short time delay. If power returns, the sequence terminates, otherwise the ATS signals the generator to
start.
- The generator will take some time (1-2 minutes) to:
- Start the prime mover (engine), possibly needing multiple re-trys.
- Engine accelerates to correct speed to produce 50 Hz.
- Excitation and automatic voltage regulation to cause correct voltage to appear 230 V on the output.
- ATS will break the connection to the mains and make it instead to the generator.
- Generator maintains frequency at 50 Hz using governor to control engine throttle, and voltage at 230 V using automatic
voltage regulator that controls the excitation current.
4.2 On return of mains power
- ATS senses return of mains power. Initiates a time delay before continuining to ensure mains power is stable.
- ATS transfers loads back to mains. Generator continues to run for a predetermined cooldown period.
- If mains power is again lost during this period, can switch back to generator almost immediately.
- Generator is stopped once cooldown period has elapsed. Ready for cycle to resume again.
5 UPS compatibility
Generators and UPS systems have a complex relationship. Although they synergise well in principle, they can both cause
problems for each other in practice.
-
Standby & line-interactive
- UPS will require the generator to maintain a very tight tolerence on voltage and
frequency. Frequent transfers to battery possible when
and
deviate due to load switching.
-
Double-conversion (AC-DC-AC)
- UPS will generally work best, as it is tolerent to incoming frequency/voltage
variations. Double-conversion UPS systems can cause major problems though for undersized generators because
their rectifiers can generate harmonics on the power input.
In general, the less dominant the UPS (and its downstream load) is as a fraction of the total load, the more successful the
UPS-generator pairing will be. More generally, a generator will be more successful powering a large number of smaller loads
than a smaller number of large loads.
6 Generator Sizing
Generators need to be sized taking into account:
- The critical load attached to the UPS.
- The battery recharging demand of the UPS.
- Inherent inefficiencies in the UPS.
- The essential loads (such as cooling).
- Large starting currents and harmonics when loads (including the UPS rectifier) are connected, particularly when
starting up.
- Expansion capacity (since a generator is a large capital investment).
This means that substantial buffer / correction factors are often applied to ensure a generator is adequately
sized.
7 Responsibility
Generators are often not managed by IT personnel, but rather facilities management. IT will need to communicate with
facilities managament both to maintain a good work relationship and to exchange data, including the setup of automated data
feeds.
8 Siting
Many generators are sited outside, but some are sited inside, depending on business needs and space planning. Consideration
must be given to:
-
Ease of interconnection
- to power system.
-
Noise
- generated in use inside and outside building.
-
Fuel storage and supply
- using inbuilt and/or external tanks, gravity or pumped supply.
-
Exhaust system
- to ensure safety of building fabric and its occupants.
-
Accessibility
- for servicing and routine maintenance and testing.
-
Cooling
- of the generator itself during operation. If inside, ventilation/cooling will be needed.
-
Security
- since sabotage could “take out” a data centre!
9 Routine maintenance
-
Starting battery
- needs to be kept charged and checked on schedule.
-
Engine-block heating
- (usually electric) should be considered in cold climates.
-
Generator must be tested
- regularly, preferably on load.